Culloden - Wyoming 765 kV

PJM queue ID AG2-466 Terminal status

Queue IDAG2-466
Project nameCulloden - Wyoming 765 kV
Status (as published)Withdrawn
SubstationCulloden - Wyoming
Point of interconnectionCulloden - Wyoming 765 kV
CountyNot reported
StateWV
Voltage765 kV
Capacity198 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-30
Source datasetcycle

Additional filed fields

DeveloperHobet Solar I, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy330.0
Mw Capacity198.0
Mfo330.0
Submitted Date3/30/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025