Substation Scout

Cedar Creek 138 kV VII

PJM queue ID AG2-447

Queue IDAG2-447
Project nameCedar Creek 138 kV VII
Status (as published)Active
SubstationCedar Creek VII
Point of interconnectionCedar Creek 138 kV VII
CountyNew Castle
StateDE
Voltage138 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperFreepoint Solar LLC
Transmission OwnerDPL
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy20.0
Mw Capacity12.0
Mfo134.25
Submitted Date3/30/2021
Last Updated5/14/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.