Substation Scout

Oxbow 34.5 kV

PJM queue ID AG2-439 Terminal status

Queue IDAG2-439
Project nameOxbow 34.5 kV
Status (as published)Withdrawn
SubstationOxbow
Point of interconnectionOxbow 34.5 kV
CountyWyoming
StatePA
Voltage34.5 kV
Capacity5.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-02-01
Source datasetcycle

Additional filed fields

DeveloperField Brook Solar LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy9.8
Mw Capacity5.3
Mfo9.8
Submitted Date3/30/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.