Substation Scout

Mount Airy - Wythe 138 kV

PJM queue ID AG2-432 Terminal status

Queue IDAG2-432
Project nameMount Airy - Wythe 138 kV
Status (as published)Withdrawn
SubstationMount Airy - Wythe
Point of interconnectionMount Airy - Wythe 138 kV
CountyWythe
StateVA
Voltage138 kV
Capacity30 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy45
Mw Capacity30
Mfo45
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.