Wakefield 115 kV

PJM queue ID AG2-428 Terminal status

Queue IDAG2-428
Project nameWakefield 115 kV
Status (as published)Withdrawn
SubstationWakefield
Point of interconnectionWakefield 115 kV
CountySussex
StateVA
Voltage115 kV
Capacity135.7 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2028-04-30
Source datasetcycle

Additional filed fields

DeveloperPeter's Bridge Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy170.0
Mw Capacity135.7
Mfo170.0
Submitted Date3/30/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.