Blain 115 kV

PJM queue ID AG2-418 Terminal status

Queue IDAG2-418
Project nameBlain 115 kV
Status (as published)Withdrawn
SubstationBlain
Point of interconnectionBlain 115 kV
CountyPerry
StatePA
Voltage115 kV
Capacity20 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-12-31
Source datasetcycle

Additional filed fields

DeveloperWills Creek Solar LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy40.0
Mw Capacity20.0
Mfo40.0
Submitted Date3/30/2021
Withdrawn Date11/13/2025
Withdrawn RemarksCIW
Last Updated10/7/2025