Greentown - Hummel Creek 138 kV

PJM queue ID AG2-412 Terminal status

Queue IDAG2-412
Project nameGreentown - Hummel Creek 138 kV
Status (as published)Withdrawn
SubstationGreentown - Hummel Creek
Point of interconnectionGreentown - Hummel Creek 138 kV
CountyGrant
StateIN
Voltage138 kV
Capacity78.4 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity78.4
Mfo100
Withdrawn Date9/12/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.