Pole 249 6094 12.47 kV

PJM queue ID AG2-388 Terminal status

Queue IDAG2-388
Project namePole 249 6094 12.47 kV
Status (as published)Withdrawn
SubstationPole 249
Point of interconnectionPole 249 6094 12.47 kV
CountyCampbell
StateVA
Voltage12.5 kV
Capacity6 MW
Resource (as published)Methane
Resource categoryGas (normalised for filtering)
Target commercial operation2022-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6
Mw Capacity6
Mfo6
Withdrawn Date12/18/2024