Substation Scout

Hillcrest 345 kV

PJM queue ID AG2-359 Terminal status

Queue IDAG2-359
Project nameHillcrest 345 kV
Status (as published)Withdrawn
SubstationHillcrest
Point of interconnectionHillcrest 345 kV
CountyBrown
StateOH
Voltage345 kV
Capacity125 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-11-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy125
Mw Capacity125
Mfo125
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.