Substation Scout

South Troy - Canton 34.5 kV

PJM queue ID AG2-356 Terminal status

Queue IDAG2-356
Project nameSouth Troy - Canton 34.5 kV
Status (as published)Withdrawn
SubstationSouth Troy - Canton
Point of interconnectionSouth Troy - Canton 34.5 kV
CountyBradford
StatePA
Voltage34.5 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-12-01
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 12 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperRobin Solar LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy20.0
Mw Capacity12.0
Mfo20.0
Submitted Date3/26/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated12/19/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.