East Elkhart - Elcona Tap 138 kV

PJM queue ID AG2-332 Terminal status

Queue IDAG2-332
Project nameEast Elkhart - Elcona Tap 138 kV
Status (as published)Withdrawn
SubstationEast Elkhart - Elcona Tap
Point of interconnectionEast Elkhart - Elcona Tap 138 kV
CountyElkhart
StateIN
Voltage138 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 100 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperAmberjack Solar LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy100.0
Mw Capacity100.0
Mfo200.0
Submitted Date3/25/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated12/22/2025