Substation Scout

Jefferson-Greentown 765 kV

PJM queue ID AG2-331 Terminal status

Queue IDAG2-331
Project nameJefferson-Greentown 765 kV
Status (as published)Withdrawn
SubstationJefferson-Greentown
Point of interconnectionJefferson-Greentown 765 kV
CountyDecatur
StateIN
Voltage765 kV
Capacity156 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Additional filed fields

DeveloperCobia Solar LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy200.0
Mw Capacity156.0
Mfo715.0
Submitted Date3/25/2021
Withdrawn Date11/27/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.