Amsden - Fremont Center 69 kV

PJM queue ID AG2-289

Queue IDAG2-289
Project nameAmsden - Fremont Center 69 kV
Status (as published)Active
SubstationAmsden - Fremont Center
Point of interconnectionAmsden - Fremont Center 69 kV
CountySeneca
StateOH
Voltage69 kV
Capacity66.6 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperChinchilla Solar LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy66.6
Mfo66.6
Submitted Date3/23/2021
Last Updated5/14/2026