Catharpin 230 kV

PJM queue ID AG2-284 Terminal status

Queue IDAG2-284
Project nameCatharpin 230 kV
Status (as published)Withdrawn
SubstationCatharpin
Point of interconnectionCatharpin 230 kV
CountyPrince William
StateVA
Voltage230 kV
Capacity150 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-12-31
Source datasetcycle

Additional filed fields

DeveloperUrban Grid Solar Projects, LLC.
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy150.0
Mw Capacity150.0
Mfo150.0
Submitted Date3/22/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025