Substation Scout

Hagerstown-Conservit 34.5 kV

PJM queue ID AG2-279 Terminal status

Queue IDAG2-279
Project nameHagerstown-Conservit 34.5 kV
Status (as published)Withdrawn
SubstationHagerstown-Conservit
Point of interconnectionHagerstown-Conservit 34.5 kV
CountyWashington
StateMD
Voltage34.5 kV
Capacity12.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-01
Source datasetcycle

Additional filed fields

DeveloperFranklin Energy, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy20.0
Mw Capacity12.9
Mfo20.0
Submitted Date3/22/2021
Withdrawn Date11/24/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.