Robinson 69 kV

PJM queue ID AG2-278 Terminal status

Queue IDAG2-278
Project nameRobinson 69 kV
Status (as published)Withdrawn
SubstationRobinson
Point of interconnectionRobinson 69 kV
CountyFayette
StateOH
Voltage69 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo60
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.