Washington-Furnace Brook Tap 34.5kV

PJM queue ID AG2-228 Terminal status

Queue IDAG2-228
Project nameWashington-Furnace Brook Tap 34.5kV
Status (as published)Withdrawn
SubstationWashington-Furnace Brook Tap
Point of interconnectionWashington-Furnace Brook Tap 34.5kV
CountyWarren
StateNJ
Voltage34.5 kV
Capacity4.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-03-31
Source datasetcycle

Additional filed fields

DeveloperReeder Farm Solar Farm, LLC
Transmission OwnerJCPL
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy11.2
Mw Capacity4.704
Mfo11.2
Submitted Date3/12/2021
Withdrawn Date6/26/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025