Substation Scout

Harwood 69 kV

PJM queue ID AG2-227 Terminal status

Queue IDAG2-227
Project nameHarwood 69 kV
Status (as published)Withdrawn
SubstationHarwood
Point of interconnectionHarwood 69 kV
CountyLuzerne
StatePA
Voltage69 kV
Capacity13.2 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy33
Mw Capacity13.2
Mfo33
Withdrawn Date11/28/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.