Substation Scout

Allen Junction 345 kV

PJM queue ID AG2-223 Terminal status

Queue IDAG2-223
Project nameAllen Junction 345 kV
Status (as published)Withdrawn
SubstationAllen Junction
Point of interconnectionAllen Junction 345 kV
CountyLucas
StateOH
Voltage345 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity100
Mfo100
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.