Substation Scout

Airey - Golden Hill 69 kV

PJM queue ID AG2-181 Terminal status

Queue IDAG2-181
Project nameAirey - Golden Hill 69 kV
Status (as published)Withdrawn
SubstationAirey - Golden Hill
Point of interconnectionAirey - Golden Hill 69 kV
CountyDorchester
StateMD
Voltage69 kV
Capacity2.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-03-01
Source datasetcycle

Additional filed fields

DeveloperOld Line Energy, LLC
Transmission OwnerDPL
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy28.0
Mw Capacity2.8
Mfo28.0
Submitted Date2/26/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.