Sewellton Junction 69 kV
PJM queue ID AG2-179 Terminal status
| Queue ID | AG2-179 |
|---|---|
| Project name | Sewellton Junction 69 kV |
| Status (as published) | Withdrawn |
| Substation | Sewellton Junction |
| Point of interconnection | Sewellton Junction 69 kV |
| County | Adair |
| State | KY |
| Voltage | 69 kV |
| Capacity | 57 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2027-11-19 |
| Source dataset | cycle |
Additional filed fields
| Developer | Round Trip, LLC |
|---|---|
| Transmission Owner | EKPC |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 60.0 |
| Mw Capacity | 57.0 |
| Mfo | 60.0 |
| Submitted Date | 2/26/2021 |
| Withdrawn Date | 12/4/2025 |
| Withdrawn Remarks | CMN |
| Last Updated | 12/3/2025 |