Substation Scout

Sewellton Junction 69 kV

PJM queue ID AG2-179 Terminal status

Queue IDAG2-179
Project nameSewellton Junction 69 kV
Status (as published)Withdrawn
SubstationSewellton Junction
Point of interconnectionSewellton Junction 69 kV
CountyAdair
StateKY
Voltage69 kV
Capacity57 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-11-19
Source datasetcycle

Additional filed fields

DeveloperRound Trip, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy60.0
Mw Capacity57.0
Mfo60.0
Submitted Date2/26/2021
Withdrawn Date12/4/2025
Withdrawn RemarksCMN
Last Updated12/3/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.