PJM queue ID AG2-159 Terminal status

Queue IDAG2-159
Project nameWilliamstown 69 kV
Status (as published)Withdrawn
SubstationWilliamstown
Point of interconnectionWilliamstown 69 kV
CountyGrant
StateKY
Voltage69 kV
Capacity57.6 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-11-19
Source datasetcycle

Additional filed fields

DeveloperRound Trip, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy61.0
Mw Capacity57.6
Mfo61.0
Submitted Date2/25/2021
Withdrawn Date12/3/2025
Withdrawn RemarksCMN