Substation Scout

Linden 12 kV

PJM queue ID AG2-155 Terminal status

Queue IDAG2-155
Project nameLinden 12 kV
Status (as published)Withdrawn
SubstationLinden
Point of interconnectionLinden 12 kV
CountyLycoming
StatePA
Voltage12 kV
Capacity1.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2.8
Mw Capacity1.4
Mfo2.8
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.