Substation Scout

River Dock 23 kV

PJM queue ID AG2-150 Terminal status

Queue IDAG2-150
Project nameRiver Dock 23 kV
Status (as published)Withdrawn
SubstationRiver Dock
Point of interconnectionRiver Dock 23 kV
CountyAllegheny
StatePA
Voltage23 kV
Capacity5.3 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2022-12-31
Source datasetcycle

Additional filed fields

DeveloperLock+ Hydro Friends Fund XLII, LLC
Transmission OwnerDL
Project TypeGeneration Interconnection
CycleTC2
StageAPPLICATION PHASE
Mw Energy5.25
Mw Capacity5.25
Mfo5.25
Submitted Date2/23/2021
Withdrawn Date4/7/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated4/7/2025