S Berwick - Galion 345 kV
PJM queue ID AG2-148 Terminal status
| Queue ID | AG2-148 |
|---|---|
| Project name | S Berwick - Galion 345 kV |
| Status (as published) | Withdrawn |
| Substation | S Berwick - Galion |
| Point of interconnection | S Berwick - Galion 345 kV |
| County | Wyandot |
| State | OH |
| Voltage | 345 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | cycle |
Additional filed fields
| Developer | Armadillo Solar LLC |
|---|---|
| Transmission Owner | AEP |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 86.0 |
| Mw Capacity | 0.0 |
| Mfo | 86.0 |
| Submitted Date | 2/22/2021 |
| Withdrawn Date | 11/27/2025 |
| Withdrawn Remarks | CIW |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.