Colby Tap-Valley 138 kV

PJM queue ID AG2-130 Terminal status

Queue IDAG2-130
Project nameColby Tap-Valley 138 kV
Status (as published)Withdrawn
SubstationColby Tap-Valley
Point of interconnectionColby Tap-Valley 138 kV
CountyVan Buren
StateMI
Voltage138 kV
Capacity37.2 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2026-12-31
Source datasetcycle

Additional filed fields

DeveloperCP Glenwood LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageAPPLICATION REVIEW
Mw Energy55.0
Mw Capacity37.2
Mfo55.0
Submitted Date2/2/2021
Withdrawn Date3/30/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated4/2/2025