Substation Scout

Gladstone 138 kV

PJM queue ID AG2-127 Terminal status

Queue IDAG2-127
Project nameGladstone 138 kV
Status (as published)Withdrawn
SubstationGladstone
Point of interconnectionGladstone 138 kV
CountyNelson
StateVA
Voltage138 kV
Capacity40 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity40
Mfo100
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.