Substation Scout

Olive-Reynolds #2 345 kV

PJM queue ID AG2-117 Terminal status

Queue IDAG2-117
Project nameOlive-Reynolds #2 345 kV
Status (as published)Withdrawn
SubstationOlive-Reynolds #2
Point of interconnectionOlive-Reynolds #2 345 kV
CountyWhite
StateIN
Voltage345 kV
Capacity60 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2023-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity60
Mfo100
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.