Substation Scout

Fitchville-New London 69 kV

PJM queue ID AG2-109

Queue IDAG2-109
Project nameFitchville-New London 69 kV
Status (as published)Active
SubstationFitchville-New London
Point of interconnectionFitchville-New London 69 kV
CountyHuron
StateOH
Voltage69 kV
Capacity28.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

DeveloperRosemary Solar, LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy40.0
Mw Capacity28.1
Mfo40.0
Submitted Date1/29/2021
Last Updated5/14/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.