Substation Scout

Milford-Cool Springs 230 kV

PJM queue ID AG2-108 Terminal status

Queue IDAG2-108
Project nameMilford-Cool Springs 230 kV
Status (as published)Withdrawn
SubstationMilford-Cool Springs
Point of interconnectionMilford-Cool Springs 230 kV
CountySussex
StateDE
Voltage230 kV
Capacity130.6 MW
Resource (as published)Offshore Wind
Resource categoryOffshore Wind (normalised for filtering)
Target commercial operation2026-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy460
Mw Capacity130.6
Mfo460
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.