Marysville-Flatlick 765 kV

PJM queue ID AG2-105 Terminal status

Queue IDAG2-105
Project nameMarysville-Flatlick 765 kV
Status (as published)Withdrawn
SubstationMarysville-Flatlick
Point of interconnectionMarysville-Flatlick 765 kV
CountyMadison
StateOH
Voltage765 kV
Capacity253.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy400
Mw Capacity253.7
Mfo800
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.