Oak Hall-Perdue 69 kV

PJM queue ID AG2-102 Terminal status

Queue IDAG2-102
Project nameOak Hall-Perdue 69 kV
Status (as published)Withdrawn
SubstationOak Hall-Perdue
Point of interconnectionOak Hall-Perdue 69 kV
CountyAccomack
StateVA
Voltage69 kV
Capacity12 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo20
Withdrawn Date12/18/2024