Substation Scout

Jamestown Tap-Maysville 69 kV

PJM queue ID AG2-041 Terminal status

Queue IDAG2-041
Project nameJamestown Tap-Maysville 69 kV
Status (as published)Withdrawn
SubstationJamestown Tap-Maysville
Point of interconnectionJamestown Tap-Maysville 69 kV
CountyMercer
StatePA
Voltage69 kV
Capacity11.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-03-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity11.8
Mfo19.8
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.