Substation Scout

Allen 13.2 kV

PJM queue ID AG2-024 Terminal status

Queue IDAG2-024
Project nameAllen 13.2 kV
Status (as published)Withdrawn
SubstationAllen
Point of interconnectionAllen 13.2 kV
CountyCumberland
StatePA
Voltage13.2 kV
Capacity2.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3
Mw Capacity2.1
Mfo3
Withdrawn Date10/15/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.