Hampton BESS 3
PJM queue ID AG2-010 Terminal status
| Queue ID | AG2-010 |
|---|---|
| Project name | Hampton BESS 3 |
| Status (as published) | Withdrawn |
| Substation | Peninsula-Whealton |
| Point of interconnection | Peninsula-Whealton 115 kV |
| County | City of Hampton |
| State | VA |
| Voltage | 115 kV |
| Capacity | 76 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Delorean Power LLC dba Lightshift Energy |
|---|---|
| Transmission Owner | Dominion |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 100.0 |
| Mw Capacity | 75.96 |
| Mfo | 100.0 |
| Submitted Date | 10/9/2020 |
| Withdrawn Date | 11/19/2025 |
| Withdrawn Remarks | CIW |
| Last Updated | 10/30/2025 |