East Sidney-Quincy 138 kV

PJM queue ID AG2-004 Terminal status

Queue IDAG2-004
Project nameEast Sidney-Quincy 138 kV
Status (as published)Withdrawn
SubstationEast Sidney-Quincy
Point of interconnectionEast Sidney-Quincy 138 kV
CountyChampaign
StateOH
Voltage138 kV
Capacity8.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity8.4
Mfo164
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.