Taylor Creek
PJM queue ID AG1-562 Terminal status
| Queue ID | AG1-562 |
|---|---|
| Project name | Taylor Creek |
| Status (as published) | Withdrawn |
| Substation | Marysville-Gunn Road |
| Point of interconnection | Marysville-Gunn Road 345 kV |
| County | Hardin |
| State | OH |
| Voltage | 345 kV |
| Capacity | 150 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-03-31 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 250 |
| Mw Capacity | 150 |
| Mfo | 250 |
| Withdrawn Date | 1/28/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.