Parnell Solar

PJM queue ID AG1-551 Terminal status

Queue IDAG1-551
Project nameParnell Solar
Status (as published)Withdrawn
SubstationParmele
Point of interconnectionParmele 34.5 kV
CountyMartin
StateNC
Voltage34.5 kV
Capacity13.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-15
Source datasetcycle

Additional filed fields

DeveloperParnell Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy19.99
Mw Capacity13.1
Mfo19.99
Submitted Date9/30/2020
Withdrawn Date11/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated11/4/2025