Substation Scout

Keystone 230 kV

PJM queue ID AG1-549 Terminal status

Queue IDAG1-549
Project nameKeystone 230 kV
Status (as published)Withdrawn
SubstationKeystone
Point of interconnectionKeystone 230 kV
CountyArmstrong
StatePA
Voltage230 kV
Capacity85 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2022-10-31
Source datasetcycle

Additional filed fields

DeveloperPlum Creek Energy, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy100.0
Mw Capacity85.0
Mfo100.0
Submitted Date9/30/2020
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated1/27/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.