Berry Hill 138 kV

PJM queue ID AG1-540 Terminal status

Queue IDAG1-540
Project nameBerry Hill 138 kV
Status (as published)Withdrawn
SubstationBerry Hill
Point of interconnectionBerry Hill 138 kV
CountyPittsylvania
StateVA
Voltage138 kV
Capacity21.4 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy55
Mw Capacity21.35
Mfo55
Withdrawn Date3/5/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.