Substation Scout

Barterbrook-Stuarts Draft 115 kV

PJM queue ID AG1-537 Terminal status

Queue IDAG1-537
Project nameBarterbrook-Stuarts Draft 115 kV
Status (as published)Withdrawn
SubstationBarterbrook-Stuarts Draft
Point of interconnectionBarterbrook-Stuarts Draft 115 kV
CountyAugusta
StateVA
Voltage115 kV
Capacity32 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-10-01
Source datasetcycle

Additional filed fields

DeveloperChestnut Storage, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy75.0
Mw Capacity32.0
Mfo75.0
Submitted Date9/30/2020
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated1/27/2025