Substation Scout

Springdale

PJM queue ID AG1-514 Terminal status

Queue IDAG1-514
Project nameSpringdale
Status (as published)Withdrawn
SubstationSpringdale CT III
Point of interconnectionSpringdale CT III 138 kV
CountyAllegheny
StatePA
Voltage138 kV
Capacity4 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity4
Mfo106
Withdrawn Date8/14/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.