Substation Scout

Marlow-Bedington 138 kV

PJM queue ID AG1-458 Terminal status

Queue IDAG1-458
Project nameMarlow-Bedington 138 kV
Status (as published)Withdrawn
SubstationMarlow-Bedington
Point of interconnectionMarlow-Bedington 138 kV
CountyWashington
StateMD
Voltage138 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy40
Mw Capacity24
Mfo40
Withdrawn Date3/1/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.