Springboro-Venango Junction 115 kV

PJM queue ID AG1-455 Terminal status

Queue IDAG1-455
Project nameSpringboro-Venango Junction 115 kV
Status (as published)Withdrawn
SubstationSpringboro-Venango Junction
Point of interconnectionSpringboro-Venango Junction 115 kV
CountyCrawford
StatePA
Voltage115 kV
Capacity35 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy35
Mw Capacity35
Mfo112.5
Withdrawn Date12/3/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.