Rawlings-Carson 500 kV

PJM queue ID AG1-449 Terminal status

Queue IDAG1-449
Project nameRawlings-Carson 500 kV
Status (as published)Withdrawn
SubstationRawlings-Carson
Point of interconnectionRawlings-Carson 500 kV
CountyDinwiddie
StateVA
Voltage500 kV
Capacity122 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-31
Source datasetcycle

Additional filed fields

DeveloperRWE Solar Development, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy122.0
Mw Capacity122.0
Mfo436.0
Submitted Date9/30/2020
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated1/27/2025