Curdsville DP-Willis Mt. 115 kV

PJM queue ID AG1-432 Terminal status

Queue IDAG1-432
Project nameCurdsville DP-Willis Mt. 115 kV
Status (as published)Withdrawn
SubstationCurdsville DP-Willis Mt.
Point of interconnectionCurdsville DP-Willis Mt. 115 kV
CountyBuckingham
StateVA
Voltage115 kV
Capacity120 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetcycle

Additional filed fields

DeveloperACE Development Company II, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy200.0
Mw Capacity120.0
Mfo200.0
Submitted Date9/30/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024