Flowing Springs Farm
PJM queue ID AG1-416 Terminal status
| Queue ID | AG1-416 |
|---|---|
| Project name | Flowing Springs Farm |
| Status (as published) | Withdrawn |
| Substation | Sleepy Hollow |
| Point of interconnection | Sleepy Hollow 138 kV |
| County | Jefferson |
| State | WV |
| Voltage | 138 kV |
| Capacity | 91 MW |
| Resource (as published) | Solar; Storage |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2028-08-31 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 125 |
| Mw Capacity | 91 |
| Mfo | 125 |
| Withdrawn Date | 6/26/2025 |