Substation Scout

Blue Mound-Chestnut 345 kV

PJM queue ID AG1-403 Terminal status

Queue IDAG1-403
Project nameBlue Mound-Chestnut 345 kV
Status (as published)Withdrawn
SubstationBlue Mound-Chestnut
Point of interconnectionBlue Mound-Chestnut 345 kV
CountyMcLean
StateIL
Voltage345 kV
Capacity33.1 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2024-09-24
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy188
Mw Capacity33.1
Mfo188
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.