PJM queue ID AG1-375 Terminal status

Queue IDAG1-375
Project nameBlackford County Solar
Status (as published)Withdrawn
SubstationSorenson-Desoto
Point of interconnectionSorenson-Desoto 345 kV
CountyBlackford
StateIN
Voltage345 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-10-31
Source datasetcycle

Additional filed fields

DeveloperBlackford County Wind Farm LLC d/b/a Blackford County Solar Park LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy100.0
Mw Capacity60.0
Mfo300.0
Submitted Date9/30/2020
Withdrawn Date11/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated2/17/2026