Nelson-Electric Junction 345 kV

PJM queue ID AG1-372 Terminal status

Queue IDAG1-372
Project nameNelson-Electric Junction 345 kV
Status (as published)Withdrawn
SubstationNelson-Electric Junction
Point of interconnectionNelson-Electric Junction 345 kV
CountyLee
StateIL
Voltage345 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-11-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity20
Mfo200
Withdrawn Date3/16/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.